We have decided to go with updating source of funding but not contracting organisation – so we have source of funding 105-SFA and contracting org remains as it was before year start i.e YPxx
Which is at odds with Sharon's advice (and LIS) but the OLDC seems to like it…
-
Alan Taws posted on the forum topic 16-18 LR learner turned 19 in the group Data Issues: 3 days, 19 hours ago
Thanks Sharon – but this problem occurs for all the UKPRNs I manage so it seems like the OLDC has nothing in place to ensure funding for 16-18 learners who have turned 19 before August. Bearing in mind that the R06 will be used to determine our allocation for next year, I'd appreciate some assurance [...]
-
Alan Taws started the forum topic 16-18 LR learner turned 19 in the group Data Issues: 3 days, 19 hours ago
Can somebody please clarify the changes needed when a learner has carried into the new academic year after turning 19 – so source of funding was oriignally set to 107-YPLA and contracting org set to a YP region code.
Guidance on the IA FAQs states that source of funding needs to be changed to 105-SFA [...] -
Alan Taws started the forum topic 16-18 LR learner turned 19 funding in the group Own Software Writers Group: 6 days, 18 hours ago
I've got quite a lot of Foundation Learning learners who started age 16-18 but have turned 19 before the start of the new academic year. Guidance states we changes Source of Funding to 105-SFA and change contracting organisation to an SFA regional code (doesn't apply to colleges).
My problem with this is that I was [...] -
Alan Taws posted on the forum topic LIS V19 in the group Data Service Software: 2 weeks, 6 days ago
Does anyone have the direct email address for reporting LIS bugs -I had it as CVH-LISLADqueries@lsc.gov.uk but guessing that no longer exists?
-
Alan Taws posted on the forum topic ILR Change Request 8 – Improving the availability and collection of data on the economic activity st in the group Data Issues: 2 months, 1 week ago
Providing you capture employment status prior to programme start and employment status as and when it changes (including the date) then you can derive employment status for any point during a learner's programme. Capturing it for the start of each learning aim (DBS) is just clumsy.
You could remove the EmpStatType field altogether as that [...] -
Alan Taws posted on the forum topic Success Rate Methodology in the group Own Software Writers Group: 2 months, 2 weeks ago
OK – now they've published the 2010/11 QSR methodology… had a quick look and it does seem that they won't count late achievers as success – and unlike ER timely success there doesn't appear to be a 90 day period of leniency.
So can I take that all our FL learners who were still beavering away [...]
-
Alan Taws posted on the forum topic Should we ask for R04 to be postponed in the group Data Issues: 2 months, 2 weeks ago
I think Paul must have had tongue firmly in cheek with that statement… either that or he secretly wants to be an MI supplier? btw still not getting notifications on posts that i'm subscribed to.
-
Alan Taws posted on the forum topic Should we ask for R04 to be postponed in the group Data Issues: 2 months, 2 weeks ago
That was exciting… or is it just me?
Anyhow, provider MIS difficulties, case in hand, would seem a stronger argument for delaying the R04. -
Alan Taws posted on the forum topic Success Rate Methodology in the group Own Software Writers Group: 2 months, 2 weeks ago
Thanks Martin – I did take a look at the 2009/10 methodology and I'm 100% sure that FL will not be excluded from success rates. E2E was excluded because it wasn't aimed at delivering qualifications whereas FL is.
The 2009/10 LR methodolgy is totally innapropriate for providers who recruit to FL throughout the year – not [...] -
Alan Taws posted on the forum topic Should we ask for R04 to be postponed in the group Data Issues: 2 months, 2 weeks ago
My own experience is that LIS works fine as far as data validation goes. We've supplied fully validated LR and ER data without problem but I do think that the current LIS is relaxing a lot of rules that in some future release may be re-enabled and come back to haunt us…
With regards to WithdrawReason, [...] -
Alan Taws posted on the forum topic Success Rate Methodology in the group Own Software Writers Group: 2 months, 2 weeks ago
Still confused. What I do know for sure is that for ER Overall success is counted by the later occuring of either the planned end year or the actual end year (Timely is based purely on planned year). For LR all the guidance I've seen suggests that it is only the planned end year that [...]
-
Alan Taws posted on the forum topic LR05 deadline in the group Data Issues: 2 months, 2 weeks ago
Thanks Fazia – logged in now. Temporary glitch
-
Alan Taws started the forum topic LR05 deadline in the group Data Issues: 2 months, 2 weeks ago
Some of our operations are trying to do last minute LR05 uploads – hard close deadline 6pm tonight but OLDC seems to be overloaded, can't logon and the service desk aren't answering the phone. I'm sure this has happened before – do they normally grant an extension in these circumstances?
-
Alan Taws posted on the forum topic Should we ask for R04 to be postponed in the group Data Issues: 2 months, 2 weeks ago
I'm not sure that requesting postponement of the return is going to solve anything – the problem doesn't seem to lie with the return. The problem lies with the way the return is interpreted and therefore I'd rather press for some sort of delay to any re-profiling MCV exercises – I've not seen anything to [...]
-
Alan Taws posted on the forum topic Success Rate Methodology in the group Own Software Writers Group: 3 months, 2 weeks ago
I haven't asked the Data Service Desk – they're very busy at the moment and will almost certainly tell me to read the guidance
We have planned end dates falling right across the year – I need clarification of the following example..
A Foundation Learning aim (LR) has planned end date of 20th June 2011. The [...]
-
Alan Taws started the forum topic Success Rate Methodology in the group Own Software Writers Group: 3 months, 3 weeks ago
Just wondering if anyone can advise on a specific scenario in relation to success rate calculations for LR provision – specifically for Foundation Learning with a non college provider. With us having roll on roll off style enrolments it's common for a qualification to have an actual leave date falling after the intended leave [...]
-
Alan Taws started the forum topic OLDC upload in the group Data Issues: 4 months ago
We managed to succesfully upload to OLDC yesterday – just a few warnings in LIS but the OLDC had one major problem with our data…. as per guidance issued recently, we updated the contracting organisation code in all our Learner Responsive ILR records with a YP regional code i.e. we replaced all the LAxxx [...]
-
Alan Taws posted on the forum topic Employment status data requirements in the group Data Issues: 4 months ago
Same here Martin – no email notification. And no answers…
-
Alan Taws started the forum topic Employment status data requirements in the group Data Issues: 4 months, 2 weeks ago
I struggling to find clarification of exactly what employment data is needed for ESF purposes – in particular for programmes which have ESF match funding data requirements.
Before introduction of the Single ILR and it's dedicated, FDL, DBS and CES records we would capture A66 employment status on day before starting and A67 length of [...] -
Alan Taws started the forum topic Amalgamation in the group Own Software Writers Group: 5 months, 3 weeks ago
Finally got round to merging two XML files – had to give each file a different transmission number as LIS beta refuses to let me add 2 files with the same name – but each file when validated in isolation has 0 errors and just one or two warnings about postcodes.
Must be doing something [...]
-
Alan Taws posted on the forum topic Access to Apprenticeship guidance in the group Data Issues: 5 months, 3 weeks ago
Unless I've really misunderstood everything an Intermediate Level has always been a code 3 even though Intermediate represents level 2 provision. And Advanced has always been a code 2 even though it represents level 3 provision. i.e. everything has always been completely backward.
I was just wondering/hoping that they might actually fix this.
-
Alan Taws started the forum topic Access to Apprenticeship guidance in the group Data Issues: 6 months ago
I've just received the document "NAS-AccesstoApprenticeships-ILRreportingtechnicaldocument-29July2011.pdf" – it's guidance from the NAS explaining how to record an Access to Apprenticeship learner on the ILR….
The first line states that the Programme Type field will be recorded as code 1 'Intermediate Level Apprenticeship' or code 2 for Advanced….
Surely Intermediate is still a code 3 – or have [...] -
Alan Taws started the forum topic Transfer of learners under MCL in the group Own Software Writers Group: 6 months, 1 week ago
We will be transferring many of our ER learners due to Minimum Contract Levels but the data will remain in the original providers MI and continue to be batch exported from there over to the lead provider who will merge with their own batch (using LIS) – guidance states such learners should be flagged in [...]
-
Alan Taws posted on the forum topic Population of A71 – Full or Co Funding in the group Own Software Writers Group: 6 months, 3 weeks ago
Apprenticeship aims are typically either full or co-funded depending on their age at start of the programme – not the age at start of the component aim – and if the learner has a break in learning and returns after turning 19 then they are still entitled to full funding – everything would still [...]